Communiqué de presse de Nava sur les résultats 2025
Posté : ven. 6 févr. 2026 13:46
https://www.navalimited.com/wp-content/ ... eb2026.pdf
Voici ce qui concerne Maamba:
• Maamba Energy Limited (MEL) realised US$ 20 million towards arrears during the quarter, reducing outstanding arrears from ZESCO to US$ 30.5 million, underscoring continued focus on cash flow discipline.
• MEL continued to distribute dividends which cumulatively stood at US$ 89.5 million to Nava Global, enabling it to pay dividends to and buy back shares from Nava.
Project Updates
• Solar Energy: Construction of MSEL’s 100 MW solar power project in Zambia commenced in September 2025 and remains on track for commissioning in H1 FY27.
• MEL’s 300 MW Expansion: Continues to progress strongly with majority equipment dispatched / delivered to site and erection works being in full swing. The Company expects a slight delay in commissioning of the project which is now expected in H2 FY27.
• Maamba Energy Limited (MEL) a recouvré 20 millions de dollars américains d'arriérés au cours du trimestre, réduisant ainsi les arriérés impayés de ZESCO à 30,5 millions de dollars américains, ce qui souligne l'importance accordée à la discipline en matière de flux de trésorerie.
• MEL a continué à distribuer des dividendes qui se sont élevés à 89,5 millions de dollars US à Nava Global, ce qui lui a permis de verser des dividendes à Nava et de racheter des actions de cette dernière.
Mise à jour des projets
• Énergie solaire : la construction du projet d'énergie solaire de 100 MW de MSEL en Zambie a débuté en septembre 2025 et reste en bonne voie pour une mise en service au premier semestre de l'exercice 2027.
• Extension de 300 MW de MEL : le projet continue de progresser à un rythme soutenu, la plupart des équipements ayant été expédiés/livrés sur le site et les travaux de montage battant leur plein. La société prévoit un léger retard dans la mise en service du projet, désormais prévue au second semestre de l'exercice 2027.
Voici ce qui concerne Maamba:
• Maamba Energy Limited (MEL) realised US$ 20 million towards arrears during the quarter, reducing outstanding arrears from ZESCO to US$ 30.5 million, underscoring continued focus on cash flow discipline.
• MEL continued to distribute dividends which cumulatively stood at US$ 89.5 million to Nava Global, enabling it to pay dividends to and buy back shares from Nava.
Project Updates
• Solar Energy: Construction of MSEL’s 100 MW solar power project in Zambia commenced in September 2025 and remains on track for commissioning in H1 FY27.
• MEL’s 300 MW Expansion: Continues to progress strongly with majority equipment dispatched / delivered to site and erection works being in full swing. The Company expects a slight delay in commissioning of the project which is now expected in H2 FY27.
• Maamba Energy Limited (MEL) a recouvré 20 millions de dollars américains d'arriérés au cours du trimestre, réduisant ainsi les arriérés impayés de ZESCO à 30,5 millions de dollars américains, ce qui souligne l'importance accordée à la discipline en matière de flux de trésorerie.
• MEL a continué à distribuer des dividendes qui se sont élevés à 89,5 millions de dollars US à Nava Global, ce qui lui a permis de verser des dividendes à Nava et de racheter des actions de cette dernière.
Mise à jour des projets
• Énergie solaire : la construction du projet d'énergie solaire de 100 MW de MSEL en Zambie a débuté en septembre 2025 et reste en bonne voie pour une mise en service au premier semestre de l'exercice 2027.
• Extension de 300 MW de MEL : le projet continue de progresser à un rythme soutenu, la plupart des équipements ayant été expédiés/livrés sur le site et les travaux de montage battant leur plein. La société prévoit un léger retard dans la mise en service du projet, désormais prévue au second semestre de l'exercice 2027.