Maamba Thermal power readies

Maamba Thermal power readies
Maamba Thermal Power plant CEO, Venkat Shankar, has said the 800 million dollar Maamba thermal power plant project has reached pre-commissioning stage.

Shankar said the tests on the plant are going on smoothly with some adjustments being made to reach the required parameters.

He however did not disclosed when the plant would fully start generating electricity for commercial use but was quick to state that the plant is close to doing so.

Shankar further said the tests on the plant have been going on for over a month now.

The Maamba Thermal Power Plant will start producing 150 mega watt, which will be increased to 300 mega watts - http://www.znbc.co.zm/.
Ce que l'on conçoit bien, s'énonce clairement, Et les mots pour le dire arrivent aisément. BOILEAU
<<

Laf1986

Messages: 4998

Inscription: Jeu 30 Juil 2009 19:54

Message Mar 28 Juin 2016 08:30

Re: Maamba Thermal power readies

On time for zambian elections
<<

mbury

Messages: 2310

Inscription: Sam 19 Sep 2009 09:49

Localisation: Nord de l'Alsace, dans le Parc Régional des Vosges du nord

Message Mar 28 Juin 2016 08:44

Re: Maamba Thermal power readies

Laf1986 a écrit:On time for zambian elections

Même si projet quasi privé, tout est bon à prendre...! Pénurie en énergie énorme, au moins le courant sera vendu facilement!