Sese power plant to cost P15bn

Sese power plant to cost P15bn

Australian junior miner, African Energy in partnership with Canadian major, First Quantum Minerals (FQM) will invest as much as $1.5 billion (P15 billion) to develop an integrated project in the eastern district of Botswana.
ByBRIAN BENZA Fri 12 Jun 2015, 18:04 pm (GMT +2) 0 Comments Email Share
: Artistic impression of Sese Power Plant
Expand this Image


The project comprises 600MW power station and a 2.5 million tonnes per annum coal mine.

Speaking at the 13th Resource Sector conference on Wednesday, African Energy managing director Fraser Tabeart said First Quantum is increasing its stake in the Sese Integrated Energy Project from 51 percent to 75 percent for a further $12 million investment.

“At the moment we have water, environmental and surface rights approvals for a 300MW Project and 1.2 million tonnes per annum coal mine. The plan is to double the capacity to 600MW and 2.5 million tonnes per annum respectively. First Quantum will take about half of the power to its Zambia copper mine operations with the rest supplied to other markets,” he said.

First Quantum, which will fully fund the project, is expected to make the final decision on the scope of the project in early 2016.

FQM produces over 400,000 tonnes of copper per annum at Zambia’s largest copper mine, Kansanshi.

African Energy, according to Tabeart, is preparing to apply for mining licence with the government of Botswana. African Energy’s partnership with a major mining company mirrors similar developments in the rest of the local coal mining industry as most junior coal miners are looking to partner with larger companies with stronger balance sheets to develop coal mining and power projects. Most junior miners have balance sheets of under $10 million when it requires between $700 million and $900 million to set up a 300MW power station. Botswana junior coal explorer, Shumba Coal has partnered with a South African firm, Mulilo Renewable Project Developments, for the joint development of the Mabesekwa Export Independent Power Plant (MEIPP), which will export power to the neighbouring country.

The MEIPP is a 300 MW energy capacity project with a minimum 260 MW net supply, to grid after auxiliary and mine consumption. The project will entail building a coal-fired power plant with a captive coalmine, to take part in the South African Coal Base Load Independent Power Producers (IPP) programme. Last year, South Africa invited IPPs to submit proposals to build coal-fired plants as part of a string of initiatives aimed at ending chronic electricity shortages there.

Another coal firm Jindal, which owns 2.7 billion tonnes of coal resources in the Mmamabula coalfields, also recently announced plans to offload 74 percent of their company to South Africa’s Glendal Trading. Due to the depressed coal prices coupled with the lack of suitable evacuation infrastructure to the sea, most coal focused mining companies have shifted focus from exports to power generation.

Jindal, which was granted a mining licence in October last year plans to set up a 600MW power plant at Mmamabula with the off-takers likely to be from South Africa’s Eskom. There are potentially nine mines on the 2,7 million Mmamabula resources, with six of them earmarked to be underground and three open casts.

- See more at: http://www.mmegi.bw/index.php?aid=51863 ... o47oD.dpuf
Ce que l'on conçoit bien, s'énonce clairement, Et les mots pour le dire arrivent aisément. BOILEAU
<<

mbury

Messages: 2310

Inscription: Sam 19 Sep 2009 09:49

Localisation: Nord de l'Alsace, dans le Parc Régional des Vosges du nord

Message Dim 14 Juin 2015 01:58

Re: Sese power plant to cost P15bn

Là, dans l'article, il est question de 400 000 tonnes de Cu produits par Kansanshi...or dans les CR , il n'en apparaît que 250 à 270 000 tonnes.
Lézard sous roche....???
<<

Laf1986

Messages: 4998

Inscription: Jeu 30 Juil 2009 19:54

Message Dim 14 Juin 2015 08:43

Re: Sese power plant to cost P15bn

Kansanshi augmente sa production pour les prochaines annees (cf ak qui vient d etre realise)
<<

mbury

Messages: 2310

Inscription: Sam 19 Sep 2009 09:49

Localisation: Nord de l'Alsace, dans le Parc Régional des Vosges du nord

Message Dim 14 Juin 2015 09:21

Re: Sese power plant to cost P15bn

Laf1986 a écrit:Kansanshi augmente sa production pour les prochaines annees (cf ak qui vient d etre realise)

Laf1986, je sais bien qu'il est question d'augmenter la production, mais il est clairement dit que Kansanshi "produit", pas qu'il "produira"...Le temps de construire une centrale pour produire du courant n'est pas comptée en mois, mais en années. De plus, pour le moment, les bénéfices énormes des dernières années ont servi à developper "Sentinel", crédit gratuit .... dont ceux de ZCCM-IH
<<

LesCrozes

Avatar de l’utilisateur

Membre d'honneur

Messages: 5910

Inscription: Jeu 14 Mai 2009 16:23

Message Dim 14 Juin 2015 11:48

Re: Sese power plant to cost P15bn

mbury a écrit:De plus, pour le moment, les bénéfices énormes des dernières années ont servi à developper "Sentinel", crédit gratuit .... dont ceux de ZCCM-IH

Le CEO continue le combat du précédent CEO pour faire que ce crédit gratuit soit enfin reconnu par First Quantum et que nous recevions une compensation.
Ce que l'on conçoit bien, s'énonce clairement, Et les mots pour le dire arrivent aisément. BOILEAU
<<

Laf1986

Messages: 4998

Inscription: Jeu 30 Juil 2009 19:54

Message Dim 14 Juin 2015 12:14

Re: Sese power plant to cost P15bn

Notre interet est que cela egalement force FQM a verse des dividendes de kansanshi du fait qu ils ne pourront plus utiliser gratuitement cette facicilite de credit

Retourner vers About Kansanshi - First Quantum Minerals

Powered by phpBB - Designed by Vjacheslav Trushkin for Free Forums/DivisionCore - Traduction par: phpBB-fr.com